Speyside Biomass CHP Plant
Speyside Biomass CHP Plant is operational in Moray with a recorded capacity of 12.5 MW, and has been generating since 2016-06-24.
Planning and build timeline
| Application submitted | 2012-08-27 |
| Permission granted | 2013-03-08 6 months after submission |
| Operational | 2016-06-24 40 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rothes Bio-Plant Biomass (dedicated) · Operational | 8.3 | 3.5 km |
Glenfiddich Distillery Anaerobic Digestion · Operational | 1.5 | 6.8 km |
Garbet Windfarm - Wind Farm & Storage facility Battery · Under Construction | 3 | 7.2 km |
Garbet Windfarm - Wind Farm & Storage facility Wind Onshore · Under Construction | 46.2 | 7.2 km |
Rothes Wind (Cairn Uish) Wind Onshore · Operational | 50.6 | 10.4 km |
Rothes Wind Farm (Extension) (II) Wind Onshore · Operational | 41.4 | 10.4 km |
Edintore Wind Farm Wind Onshore · Operational | 18 | 14.8 km |
How big is Speyside Biomass CHP Plant?
Speyside Biomass CHP Plant has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Speyside Biomass CHP Plant?
REPD records the operator as Speyside Renewable Energy Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Speyside Biomass CHP Plant approved and built?
The application was submitted on 2012-08-27. Permission was granted on 2013-03-08, 6 months later. The site became operational on 2016-06-24, 40 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 186.