Porvair International Ltd

Porvair International Ltd is operational in King's Lynn and West Norfolk with a recorded capacity of 1.8 MW, and has been generating since 2012-10-04.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-10-04
Solar Photovoltaics
Technology
KL Technologies
King's Lynn and West Norfolk
Authority
England

Planning and build timeline

Application submitted2011-01-17
Permission granted2011-03-09
2 months after submission
Operational2012-10-04
19 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

King's Lynn and West Norfolk’s record on solar

King's Lynn and West Norfolk has decided 31 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in King's Lynn and West Norfolk

Other built sites within 15 km

SiteMWDistance
K L Technologies Wind Turbine
Wind Onshore · Operational
1.50.2 km
Chamber 16 (Cold Store)
Solar Photovoltaics · Operational
1.24 km
Blackborough End Landfill Site
Landfill Gas · Operational
1.59.4 km
Sutton Bridge Solar Farm
Solar Photovoltaics · Operational
49.913.2 km
Walpole Bank
Solar Photovoltaics · Under Construction
4013.8 km
Rose And Crown Farm
Solar Photovoltaics · Operational
3014.4 km

How big is Porvair International Ltd?

Porvair International Ltd has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Porvair International Ltd?

REPD records the operator as KL Technologies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Porvair International Ltd approved and built?

The application was submitted on 2011-01-17. Permission was granted on 2011-03-09, 2 months later. The site became operational on 2012-10-04, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1340.