Chamber 16 (Cold Store) is an operational 1.2 MW solar farm in King's Lynn and West Norfolk, generating since 7 June 2016. Planning permission was granted on 11 June 2015, 4 months after submission. Operator of record: Pinguin Foods UK.
Planning and build timeline
| Application submitted | 24 February 2015 |
| Permission granted | 11 June 2015 4 months after submission |
| Operational | 7 June 2016 12 months after consent |
Screening a site of your own?
King's Lynn and West Norfolk approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Chamber 16 (Cold Store)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
King's Lynn and West Norfolk’s record on solar
King's Lynn and West Norfolk has decided 31 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in King's Lynn and West Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.8 | 4 km |
Wind Onshore · Operational | 1.5 | 4.2 km |
Landfill Gas · Operational | 1.5 | 5.4 km |
Solar Photovoltaics · Operational | 1 | 11.2 km |
How big is Chamber 16 (Cold Store)?
Chamber 16 (Cold Store) has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chamber 16 (Cold Store)?
REPD records the operator as Pinguin Foods UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chamber 16 (Cold Store) approved and built?
The application was submitted on 24 February 2015. Permission was granted on 11 June 2015, 4 months later. The site became operational on 7 June 2016, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6683.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode