Novarly ParcelRenewable sites

Renewable sitesPont Andrew Solar Farm

Pont Andrew Solar Farm

Pont Andrew Solar Farm is operational in Carmarthenshire with a recorded capacity of 1.5 MW, and has been generating since 2012-07-31.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-07-31
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted2010-11-29
Permission granted2011-04-22
5 months after submission
Operational2012-07-31
15 months after consent

Carmarthenshire’s record on solar

Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire

Other built sites within 15 km

SiteMWDistance
Pentre farm
Solar Photovoltaics · Operational
5.52.1 km
Clawdd Ddu PV
Solar Photovoltaics · Operational
13.56.9 km
Brynteg Farm
Solar Photovoltaics · Operational
16.27.5 km
Pen Y Cae solar farm
Solar Photovoltaics · Operational
6.97.6 km
Saron Road solar park
Solar Photovoltaics · Operational
6.78.5 km
Nant y Caws Landfill Site
Landfill Gas · Operational
1.48.9 km
Ffos Las Racecourse
Solar Photovoltaics · Operational
5.58.9 km
Land South Of Bryn Cyrnau Isaf
Solar Photovoltaics · Operational
5.911.8 km

How big is Pont Andrew Solar Farm?

Pont Andrew Solar Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pont Andrew Solar Farm?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pont Andrew Solar Farm approved and built?

The application was submitted on 2010-11-29. Permission was granted on 2011-04-22, 5 months later. The site became operational on 2012-07-31, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1356.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council