Pont Andrew Solar Farm
Pont Andrew Solar Farm is operational in Carmarthenshire with a recorded capacity of 1.5 MW, and has been generating since 2012-07-31.
Planning and build timeline
| Application submitted | 2010-11-29 |
| Permission granted | 2011-04-22 5 months after submission |
| Operational | 2012-07-31 15 months after consent |
Carmarthenshire’s record on solar
Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pentre farm Solar Photovoltaics · Operational | 5.5 | 2.1 km |
Clawdd Ddu PV Solar Photovoltaics · Operational | 13.5 | 6.9 km |
Brynteg Farm Solar Photovoltaics · Operational | 16.2 | 7.5 km |
Pen Y Cae solar farm Solar Photovoltaics · Operational | 6.9 | 7.6 km |
Saron Road solar park Solar Photovoltaics · Operational | 6.7 | 8.5 km |
Nant y Caws Landfill Site Landfill Gas · Operational | 1.4 | 8.9 km |
Ffos Las Racecourse Solar Photovoltaics · Operational | 5.5 | 8.9 km |
Land South Of Bryn Cyrnau Isaf Solar Photovoltaics · Operational | 5.9 | 11.8 km |
How big is Pont Andrew Solar Farm?
Pont Andrew Solar Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pont Andrew Solar Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pont Andrew Solar Farm approved and built?
The application was submitted on 2010-11-29. Permission was granted on 2011-04-22, 5 months later. The site became operational on 2012-07-31, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1356.