Renewable sites › Saron Road solar park
Saron Road solar park
Saron Road solar park is operational in Carmarthenshire with a recorded capacity of 6.7 MW, and has been generating since 2015-02-15.
Planning and build timeline
| Application submitted | 2013-04-12 |
| Permission granted | 2013-09-19 5 months after submission |
| Operational | 2015-02-15 17 months after consent |
Carmarthenshire’s record on solar
Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pen Y Cae solar farm Solar Photovoltaics · Operational | 6.9 | 1.1 km |
Clawdd Ddu PV Solar Photovoltaics · Operational | 13.5 | 3 km |
Cefn Betingau Farm Solar Photovoltaics · Operational | 9 | 5.2 km |
Mynydd y Betws Wind Onshore · Operational | 34.5 | 6.7 km |
Mynydd Y Gwair Wind Farm Wind Onshore · Operational | 32.8 | 7.5 km |
Pentre farm Solar Photovoltaics · Operational | 5.5 | 8.3 km |
Pont Andrew Solar Farm Solar Photovoltaics · Operational | 1.5 | 8.5 km |
Gelliwern Isaf Farm Solar Photovoltaics · Operational | 6 | 10.7 km |
How big is Saron Road solar park?
Saron Road solar park has a recorded installed capacity of 6.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Saron Road solar park?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Saron Road solar park approved and built?
The application was submitted on 2013-04-12. Permission was granted on 2013-09-19, 5 months later. The site became operational on 2015-02-15, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2355.