Renewable sites › Brynteg Farm
Brynteg Farm
Brynteg Farm is operational in Carmarthenshire with a recorded capacity of 16.2 MW, and has been generating since 2014-12-22.
Planning and build timeline
| Application submitted | 2013-09-19 |
| Permission granted | 2014-03-11 6 months after submission |
| Operational | 2014-12-22 9 months after consent |
Carmarthenshire’s record on solar
Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ffos Las Racecourse Solar Photovoltaics · Operational | 5.5 | 4.4 km |
Pentre farm Solar Photovoltaics · Operational | 5.5 | 6.4 km |
Pont Andrew Solar Farm Solar Photovoltaics · Operational | 1.5 | 7.5 km |
Dura Park Bynea Industrial Site Solar Photovoltaics · Operational | 1.4 | 7.9 km |
Clawdd Ddu PV Solar Photovoltaics · Operational | 13.5 | 11.6 km |
Gelliwern Isaf Farm Solar Photovoltaics · Operational | 6 | 12.9 km |
Pen Y Cae solar farm Solar Photovoltaics · Operational | 6.9 | 13.2 km |
Killan Farm Solar Array Extens Solar Photovoltaics · Operational | 1 | 13.3 km |
How big is Brynteg Farm?
Brynteg Farm has a recorded installed capacity of 16.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brynteg Farm?
REPD records the operator as Brynteg Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brynteg Farm approved and built?
The application was submitted on 2013-09-19. Permission was granted on 2014-03-11, 6 months later. The site became operational on 2014-12-22, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2363.
Novarly Parcel · official public data, read properly · parcel.novarly.com