Brynteg Farm
Brynteg Farm is an operational 16.2 MW solar farm in Carmarthenshire, generating since 22 December 2014. Planning permission was granted on 11 March 2014, 6 months after submission. Operator of record: Brynteg Solar.
Planning and build timeline
| Application submitted | 19 September 2013 |
| Permission granted | 11 March 2014 6 months after submission |
| Operational | 22 December 2014 9 months after consent |
Screening a site of your own?
Carmarthenshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Brynteg Farm’s recorded coordinate — swap in your own postcode or coordinates.
Carmarthenshire’s record on solar
Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5.5 | 4.4 km |
Solar Photovoltaics · Operational | 5.5 | 6.4 km |
Solar Photovoltaics · Operational | 1.5 | 7.5 km |
Solar Photovoltaics · Operational | 1.4 | 7.9 km |
Solar Photovoltaics · Operational | 13.5 | 11.6 km |
Solar Photovoltaics · Operational | 6 | 12.9 km |
Solar Photovoltaics · Operational | 6.9 | 13.2 km |
Solar Photovoltaics · Operational | 1 | 13.3 km |
How big is Brynteg Farm?
Brynteg Farm has a recorded installed capacity of 16.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brynteg Farm?
REPD records the operator as Brynteg Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brynteg Farm approved and built?
The application was submitted on 19 September 2013. Permission was granted on 11 March 2014, 6 months later. The site became operational on 22 December 2014, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2363.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode