Renewable sitesNant y Caws Landfill Site

Nant y Caws Landfill Site

Nant y Caws Landfill Site is operational in Carmarthenshire with a recorded capacity of 1.4 MW, and has been generating since 2001-12-01.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-12-01
Landfill Gas
Technology
NOVERA
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted1999-05-27
Permission granted1999-09-15
4 months after submission
Operational2001-12-01
27 months after consent

Other built sites within 15 km

SiteMWDistance
Land South Of Bryn Cyrnau Isaf
Solar Photovoltaics · Operational
5.94.3 km
Pont Andrew Solar Farm
Solar Photovoltaics · Operational
1.58.9 km
Redcourt Farm
Solar Photovoltaics · Operational
3.39.4 km
Pentre farm
Solar Photovoltaics · Operational
5.511 km
Ffos Las Racecourse
Solar Photovoltaics · Operational
5.512.5 km
Brynteg Farm
Solar Photovoltaics · Operational
16.214.1 km
Pen Y Cae solar farm
Solar Photovoltaics · Operational
6.914.2 km
Clawdd Ddu PV
Solar Photovoltaics · Operational
13.514.5 km

How big is Nant y Caws Landfill Site?

Nant y Caws Landfill Site has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nant y Caws Landfill Site?

REPD records the operator as NOVERA. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nant y Caws Landfill Site approved and built?

The application was submitted on 1999-05-27. Permission was granted on 1999-09-15, 4 months later. The site became operational on 2001-12-01, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 607.