Novarly ParcelRenewable sites

Renewable sitesNant y Caws Landfill Site

Nant y Caws Landfill Site

Nant y Caws Landfill Site is an operational 1.4 MW landfill gas site in Carmarthenshire, generating since 1 December 2001. Planning permission was granted on 15 September 1999, 4 months after submission. Operator of record: NOVERA.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2001
Landfill Gas
Technology
NOVERA
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted27 May 1999
Permission granted15 September 1999
4 months after submission
Operational1 December 2001
27 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Carmarthenshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Nant y Caws Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
5.94.3 km
Solar Photovoltaics · Operational
1.58.9 km
Solar Photovoltaics · Operational
3.39.4 km
Solar Photovoltaics · Operational
5.511 km
Solar Photovoltaics · Operational
5.512.5 km
Solar Photovoltaics · Operational
16.214.1 km
Solar Photovoltaics · Operational
6.914.2 km
Solar Photovoltaics · Operational
13.514.5 km

How big is Nant y Caws Landfill Site?

Nant y Caws Landfill Site has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nant y Caws Landfill Site?

REPD records the operator as NOVERA. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nant y Caws Landfill Site approved and built?

The application was submitted on 27 May 1999. Permission was granted on 15 September 1999, 4 months later. The site became operational on 1 December 2001, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 607.

Novarly Parcel · official public data, read properly · parcel.novarly.com