Pogbie Wind Farm 1
Pogbie Wind Farm 1 is an operational 5.1 MW onshore wind farm in East Lothian, generating since 29 March 2019. Planning permission was granted on 2 September 2009, 12 months after submission. Operator of record: Mongoose (formerly Energy Law Unlimited).
Planning and build timeline
| Application submitted | 1 September 2008 |
| Permission granted | 2 September 2009 12 months after submission |
| Operational | 29 March 2019 115 months after consent |
Screening a site of your own?
East Lothian approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pogbie Wind Farm 1’s recorded coordinate — swap in your own postcode or coordinates.
East Lothian’s record on onshore wind
East Lothian has decided 5 onshore wind schemes and approved 100%, taking a median of 10.6 months. See every onshore wind scheme decision in East Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.5 | 0.7 km |
Wind Onshore · Operational | 17.2 | 1.9 km |
Wind Onshore · Operational | 4.8 | 2 km |
Wind Onshore · Operational | 29.8 | 3.9 km |
Wind Onshore · Operational | 27.6 | 6.6 km |
Solar Photovoltaics · Operational | 0.2 | 8.3 km |
Wind Onshore · Operational | 144 | 9.1 km |
Wind Onshore · Operational | 6 | 13.2 km |
How big is Pogbie Wind Farm 1?
Pogbie Wind Farm 1 has a recorded installed capacity of 5.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pogbie Wind Farm 1?
REPD records the operator as Mongoose (formerly Energy Law Unlimited). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pogbie Wind Farm 1 approved and built?
The application was submitted on 1 September 2008. Permission was granted on 2 September 2009, 12 months later. The site became operational on 29 March 2019, 115 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4434.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode