Novarly ParcelRenewable sites

Renewable sitesHowden Farm

Howden Farm

Howden Farm is operational in East Lothian with a recorded capacity of 0.2 MW, and has been generating since 2021-01-01.

0.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-01-01
Solar Photovoltaics
Technology
Howden Eggs
East Lothian
Authority
Scotland

Planning and build timeline

Application submitted2020-03-05
Permission granted2020-04-27
2 months after submission
Operational2021-01-01
8 months after consent

East Lothian’s record on solar

East Lothian has decided 6 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in East Lothian

Other built sites within 15 km

SiteMWDistance
Pogbie Wind Farm 2
Wind Onshore · Operational
4.86.6 km
Pure Malt Products AD
Anaerobic Digestion · Operational
1.57.2 km
Pogbie Wind Farm 1
Wind Onshore · Operational
5.18.3 km
Keith Hill
Wind Onshore · Operational
4.58.7 km
Dun Law
Wind Onshore · Operational
17.210.2 km
Fallago Rig
Wind Onshore · Operational
14410.3 km
Dun Law Extension
Wind Onshore · Operational
29.812.3 km
Toddleburn
Wind Onshore · Operational
27.614.8 km

How big is Howden Farm?

Howden Farm has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Howden Farm?

REPD records the operator as Howden Eggs. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Howden Farm approved and built?

The application was submitted on 2020-03-05. Permission was granted on 2020-04-27, 2 months later. The site became operational on 2021-01-01, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7745.