Novarly ParcelRenewable sites

Renewable sitesHowden Farm

Howden Farm

Howden Farm is an operational 0.2 MW solar farm in East Lothian, generating since 1 January 2021. Planning permission was granted on 27 April 2020, 2 months after submission. Operator of record: Howden Eggs.

0.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2021
Solar Photovoltaics
Technology
Howden Eggs
East Lothian
Authority
Scotland

Planning and build timeline

Application submitted5 March 2020
Permission granted27 April 2020
2 months after submission
Operational1 January 2021
8 months after consent

Screening a site of your own?

RedlineUK · £39

East Lothian approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Howden Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

East Lothian’s record on solar

East Lothian has decided 6 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in East Lothian

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
4.86.6 km
Anaerobic Digestion · Operational
1.57.2 km
Wind Onshore · Operational
5.18.3 km
Wind Onshore · Operational
4.58.7 km
Wind Onshore · Operational
17.210.2 km
Wind Onshore · Operational
14410.3 km
Wind Onshore · Operational
29.812.3 km
Wind Onshore · Operational
27.614.8 km

How big is Howden Farm?

Howden Farm has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Howden Farm?

REPD records the operator as Howden Eggs. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Howden Farm approved and built?

The application was submitted on 5 March 2020. Permission was granted on 27 April 2020, 2 months later. The site became operational on 1 January 2021, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7745.

Novarly Parcel · official public data, read properly · parcel.novarly.com