Onshore wind planning in East Lothian

East Lothian has decided 5 onshore wind schemes and approved 100% of them, taking a median of 10.6 months to decide. Consented capacity: 59 MW. 2 applications still awaiting a decision.

100%
Approved
5 granted · 0 refused
10.6 mo
Median decision
UK 11.5 mo
59 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How East Lothian compares

Against the 75 UK authorities with 5+ onshore wind decisions, East Lothian sits in the 98th percentile for approval rate (32 points above the England average) and the 70th percentile for speed.

Decisions by year

35Approved — 1 (2012)112Approved — 1 (2016)116Approved — 1 (2024)124
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Howden Farm Turbine, Gifford - Wind Turbine
East Lothian Eggs Limited · 24/01091/P
0.9Application Submitted2024-10-14
Ruchlaw Mains, Stenton - Wind Turbine
Ruchlaw Produce Company Limited · 24/00642/P · 1.8 mo to decide
Awaiting Construction2024-08-21
Ferneylea Farm
XSCH · 15/00363/P
18Application Withdrawn2018-08-13
Pogbie Wind Farm 2
Mongoose (formerly Energy Law Unlimited/ Pogbie Windfarm) · 15/00536/P · 9.1 mo to decide
4.8Operational2016-05-06
Ferneylea Farm
CBK Galbraith · 10/00769/P · 17.5 mo to decide
1.5Operational2012-03-07
Keith Hill
G & M Hodge & Son Ltd · 09/00010/FUL · 7.9 mo to decide
25Revised2009-09-02
Pogbie Wind Farm 1
Mongoose (formerly Energy Law Unlimited) · 08/00823/FUL · 12 mo to decide
5.1Operational2009-09-02
Townhead Farm
Private Developer · 09/00385/FUL
6Application Withdrawn2009-07-17
Aikengall
Community Wind Power · 05/00216/FUL · 24.6 mo to decide
48Operational2007-03-16

Does East Lothian approve onshore wind schemes?

Yes — of the 5 onshore wind schemes East Lothian has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in East Lothian?

The median time from application to decision is 10.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has East Lothian consented?

59 MW has been consented across 5 approved schemes. A further 2 applications awaits a decision.

Other technologies in East Lothian

Solar in East LothianBattery storage in East Lothian

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.