Novarly ParcelRenewable sites

Renewable sitesCarcant Windfarm

Carcant Windfarm

Carcant Windfarm is operational in Scottish Borders with a recorded capacity of 6 MW, and has been generating since 2010-11-02.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-11-02
Wind Onshore
Technology
Greencoat UK Wind
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted2005-10-10
Permission granted2006-09-15
11 months after submission
Operational2010-11-02
50 months after consent

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

Other built sites within 15 km

SiteMWDistance
Bowbeat Emly Bank / Rough Side
Wind Onshore · Operational
31.27.4 km
Toddleburn
Wind Onshore · Operational
27.68.8 km
Dun Law Extension
Wind Onshore · Operational
29.811.3 km
Dun Law
Wind Onshore · Operational
17.211.7 km
Pogbie Wind Farm 1
Wind Onshore · Operational
5.113.2 km
Keith Hill
Wind Onshore · Operational
4.513.4 km
Drummond Moor Landfill
Landfill Gas · Operational
213.6 km
Oatslie Landfill Gas
Landfill Gas · Operational
213.7 km

How big is Carcant Windfarm?

Carcant Windfarm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carcant Windfarm?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carcant Windfarm approved and built?

The application was submitted on 2005-10-10. Permission was granted on 2006-09-15, 11 months later. The site became operational on 2010-11-02, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3214.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council