Carcant Windfarm
Carcant Windfarm is operational in Scottish Borders with a recorded capacity of 6 MW, and has been generating since 2010-11-02.
Planning and build timeline
| Application submitted | 2005-10-10 |
| Permission granted | 2006-09-15 11 months after submission |
| Operational | 2010-11-02 50 months after consent |
Scottish Borders’s record on onshore wind
Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bowbeat Emly Bank / Rough Side Wind Onshore · Operational | 31.2 | 7.4 km |
Toddleburn Wind Onshore · Operational | 27.6 | 8.8 km |
Dun Law Extension Wind Onshore · Operational | 29.8 | 11.3 km |
Dun Law Wind Onshore · Operational | 17.2 | 11.7 km |
Pogbie Wind Farm 1 Wind Onshore · Operational | 5.1 | 13.2 km |
Keith Hill Wind Onshore · Operational | 4.5 | 13.4 km |
Drummond Moor Landfill Landfill Gas · Operational | 2 | 13.6 km |
Oatslie Landfill Gas Landfill Gas · Operational | 2 | 13.7 km |
How big is Carcant Windfarm?
Carcant Windfarm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Carcant Windfarm?
REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Carcant Windfarm approved and built?
The application was submitted on 2005-10-10. Permission was granted on 2006-09-15, 11 months later. The site became operational on 2010-11-02, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3214.