Renewable sites › Fallago Rig
Fallago Rig
Fallago Rig is an operational 144 MW onshore wind farm in Scotland, generating since 31 March 2013. Planning permission was granted on 9 November 2010, 66 months after submission. Operator of record: EDF Energy Renewables.
Planning and build timeline
| Application submitted | 16 May 2005 |
| Permission granted | 9 November 2010 66 months after submission |
| Operational | 31 March 2013 29 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Fallago Rig’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.5 | 8.8 km |
Wind Onshore · Operational | 5.1 | 9.1 km |
Wind Onshore · Operational | 4.8 | 9.7 km |
Wind Onshore · Operational | 17.2 | 10.3 km |
Solar Photovoltaics · Operational | 0.2 | 10.3 km |
Wind Onshore · Operational | 29.8 | 10.9 km |
Wind Onshore · Operational | 138 | 12.5 km |
Wind Onshore · Operational | 62.5 | 12.7 km |
How big is Fallago Rig?
Fallago Rig has a recorded installed capacity of 144 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fallago Rig?
REPD records the operator as EDF Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fallago Rig approved and built?
The application was submitted on 16 May 2005. Permission was granted on 9 November 2010, 66 months later. The site became operational on 31 March 2013, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4059.