Keith Hill

Keith Hill is an operational 4.5 MW onshore wind farm in Scottish Borders, generating since 19 December 2017. Planning permission was granted on 1 April 2011, 5 months after submission. Operator of record: Sky Wind Energy.

4.5 MW
Capacity
as recorded in REPD
Operational
Status
since 19 December 2017
Wind Onshore
Technology
Sky Wind Energy
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted15 November 2010
Permission granted1 April 2011
5 months after submission
Operational19 December 2017
81 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Keith Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
5.10.7 km
Wind Onshore · Operational
17.21.8 km
Wind Onshore · Operational
4.82.7 km
Wind Onshore · Operational
29.83.6 km
Wind Onshore · Operational
27.66.3 km
Solar Photovoltaics · Operational
0.28.7 km
Wind Onshore · Operational
1448.8 km
Wind Onshore · Operational
613.4 km

How big is Keith Hill?

Keith Hill has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Keith Hill?

REPD records the operator as Sky Wind Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Keith Hill approved and built?

The application was submitted on 15 November 2010. Permission was granted on 1 April 2011, 5 months later. The site became operational on 19 December 2017, 81 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4516.