Novarly ParcelRenewable sites

Renewable sitesBerry Court Farm

Berry Court Farm

Berry Court Farm is an operational 4.2 MW solar farm in Basingstoke and Deane, generating since 1 December 2016. Planning permission was granted on 23 April 2015, 8 months after submission. Operator of record: Green Switch Solutions - SOLD.

4.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2016
Solar Photovoltaics
Technology
Green Switch Solutions - SOLD
Basingstoke and Deane
Authority
England

Planning and build timeline

Application submitted27 August 2014
Permission granted23 April 2015
8 months after submission
Operational1 December 2016
19 months after consent

Screening a site of your own?

RedlineUK · £39

Basingstoke and Deane approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Berry Court Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Basingstoke and Deane’s record on solar

Basingstoke and Deane has decided 21 solar farms and approved 86%, taking a median of 3.4 months. See every solar farm decision in Basingstoke and Deane

Other built sites within 15 km

SiteMWDistance
Battery · Operational
10.3 km
Solar Photovoltaics · Operational
2.81.8 km
Battery · Operational
1003.2 km
EfW Incineration · Operational
86.6 km
Anaerobic Digestion · Operational
1.26.8 km
Solar Photovoltaics · Operational
58.1 km
Solar Photovoltaics · Operational
1.710.2 km
Solar Photovoltaics · Operational
1.510.3 km

How big is Berry Court Farm?

Berry Court Farm has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Berry Court Farm?

REPD records the operator as Green Switch Solutions - SOLD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Berry Court Farm approved and built?

The application was submitted on 27 August 2014. Permission was granted on 23 April 2015, 8 months later. The site became operational on 1 December 2016, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2150.

Novarly Parcel · official public data, read properly · parcel.novarly.com