Renewable sites › Perth Wastewater Treatment Works
Perth Wastewater Treatment Works
Perth Wastewater Treatment Works is operational in Perth and Kinross with a recorded capacity of 0.4 MW, and has been generating since 2021-07-01.
Planning and build timeline
| Application submitted | 2019-02-01 |
| Permission granted | 2019-06-07 4 months after submission |
| Operational | 2021-07-01 25 months after consent |
Perth and Kinross’s record on solar
Perth and Kinross has decided 22 solar farms and approved 82%, taking a median of 3.3 months. See every solar farm decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Perth Wastewater Treatment Works (Extension) Battery · Operational | — | 0.2 km |
Perth Wastewater Treatment Works (Extension) Solar Photovoltaics · Operational | 0.3 | 0.2 km |
Aviva Headquarters Solar Photovoltaics · Operational | 1.8 | 4.7 km |
Jamesfield Organic Centre - Battery Storage Battery · Operational | 49 | 6.7 km |
Errol Estate Solar Photovoltaics · Operational | 13 | 6.9 km |
Binn Landfill Landfill Gas · Operational | 1.9 | 8.7 km |
Binn Farm AD (extension) Anaerobic Digestion · Operational | 1.5 | 8.8 km |
Lochelbank Wind Farm II Wind Onshore · Operational | 9.6 | 9.1 km |
How big is Perth Wastewater Treatment Works?
Perth Wastewater Treatment Works has a recorded installed capacity of 0.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Perth Wastewater Treatment Works?
REPD records the operator as Scottish Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Perth Wastewater Treatment Works approved and built?
The application was submitted on 2019-02-01. Permission was granted on 2019-06-07, 4 months later. The site became operational on 2021-07-01, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7287.
Novarly Parcel · official public data, read properly · parcel.novarly.com