Renewable sites › Jamesfield Organic Centre - Battery Storage
Jamesfield Organic Centre - Battery Storage
Jamesfield Organic Centre - Battery Storage is operational in Perth and Kinross with a recorded capacity of 49 MW, and has been generating since 2024-02-01.
Planning and build timeline
| Application submitted | 2022-05-20 |
| Permission granted | 2022-09-28 4 months after submission |
| Operational | 2024-02-01 16 months after consent |
Perth and Kinross’s record on battery storage
Perth and Kinross has decided 16 battery storage schemes and approved 88%, taking a median of 4.4 months. See every battery storage scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Errol Estate Solar Photovoltaics · Operational | 13 | 2.6 km |
Binn Landfill Landfill Gas · Operational | 1.9 | 4.7 km |
Binn Farm AD (extension) Anaerobic Digestion · Operational | 1.5 | 4.9 km |
Binn Eco Park - Wind Farm Wind Onshore · Operational | 10 | 5 km |
Binn Eco Park - EfW EfW Incineration · Under Construction | 7.3 | 5.8 km |
Perth Wastewater Treatment Works Solar Photovoltaics · Operational | 0.4 | 6.7 km |
Perth Wastewater Treatment Works (Extension) Battery · Operational | — | 6.8 km |
Perth Wastewater Treatment Works (Extension) Solar Photovoltaics · Operational | 0.3 | 6.8 km |
How big is Jamesfield Organic Centre - Battery Storage?
Jamesfield Organic Centre - Battery Storage has a recorded installed capacity of 49 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Jamesfield Organic Centre - Battery Storage?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Jamesfield Organic Centre - Battery Storage approved and built?
The application was submitted on 2022-05-20. Permission was granted on 2022-09-28, 4 months later. The site became operational on 2024-02-01, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10863.