Aviva Headquarters
Aviva Headquarters is an operational 1.8 MW solar farm in Perth and Kinross, generating since 1 November 2020. Planning permission was granted on 19 July 2019, 1 months after submission. Operator of record: Aviva.
Planning and build timeline
| Application submitted | 7 June 2019 |
| Permission granted | 19 July 2019 1 months after submission |
| Operational | 1 November 2020 15 months after consent |
Screening a site of your own?
Perth and Kinross approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Aviva Headquarters’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on solar
Perth and Kinross has decided 22 solar farms and approved 82%, taking a median of 3.3 months. See every solar farm decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | — | 4.6 km |
Solar Photovoltaics · Operational | 0.3 | 4.6 km |
Solar Photovoltaics · Operational | 0.4 | 4.7 km |
Wind Onshore · Operational | 9.6 | 8.9 km |
Battery · Operational | 49 | 10.9 km |
Landfill Gas · Operational | 1.9 | 11.4 km |
Anaerobic Digestion · Operational | 1.5 | 11.4 km |
Solar Photovoltaics · Operational | 13 | 11.6 km |
How big is Aviva Headquarters?
Aviva Headquarters has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Aviva Headquarters?
REPD records the operator as Aviva. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Aviva Headquarters approved and built?
The application was submitted on 7 June 2019. Permission was granted on 19 July 2019, 1 months later. The site became operational on 1 November 2020, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7347.