Novarly ParcelRenewable sites

Renewable sitesBinn Landfill

Binn Landfill

Binn Landfill is an operational 1.9 MW landfill gas site in Perth and Kinross, generating since 1 April 2004. Planning permission was granted on 19 June 2001, 3 months after submission. Operator of record: SITA UK / Natural Power.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2004
Landfill Gas
Technology
SITA UK / Natural Power
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted23 March 2001
Permission granted19 June 2001
3 months after submission
Operational1 April 2004
33 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Binn Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.50.2 km
Wind Onshore · Operational
100.5 km
EfW Incineration · Under Construction
7.31.1 km
Battery · Operational
494.7 km
Wind Onshore · Operational
9.66.2 km
Solar Photovoltaics · Operational
137.3 km
Solar Photovoltaics · Operational
0.48.7 km
Solar Photovoltaics · Operational
0.38.7 km

How big is Binn Landfill?

Binn Landfill has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Binn Landfill?

REPD records the operator as SITA UK / Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Binn Landfill approved and built?

The application was submitted on 23 March 2001. Permission was granted on 19 June 2001, 3 months later. The site became operational on 1 April 2004, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 715.