Renewable sites › Lochelbank Wind Farm II
Lochelbank Wind Farm II
Lochelbank Wind Farm II is operational in Perth and Kinross with a recorded capacity of 9.6 MW, and has been generating since 2011-05-25.
Planning and build timeline
| Application submitted | 2005-04-25 |
| Permission granted | 2007-08-15 28 months after submission |
| Operational | 2011-05-25 45 months after consent |
Perth and Kinross’s record on onshore wind
Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Binn Eco Park - EfW EfW Incineration · Under Construction | 7.3 | 5.5 km |
Binn Farm AD (extension) Anaerobic Digestion · Operational | 1.5 | 6 km |
Binn Landfill Landfill Gas · Operational | 1.9 | 6.2 km |
Binn Eco Park - Wind Farm Wind Onshore · Operational | 10 | 6.4 km |
Aviva Headquarters Solar Photovoltaics · Operational | 1.8 | 8.9 km |
Perth Wastewater Treatment Works (Extension) Solar Photovoltaics · Operational | 0.3 | 9 km |
Perth Wastewater Treatment Works (Extension) Battery · Operational | — | 9 km |
Perth Wastewater Treatment Works Solar Photovoltaics · Operational | 0.4 | 9.1 km |
How big is Lochelbank Wind Farm II?
Lochelbank Wind Farm II has a recorded installed capacity of 9.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lochelbank Wind Farm II?
REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lochelbank Wind Farm II approved and built?
The application was submitted on 2005-04-25. Permission was granted on 2007-08-15, 28 months later. The site became operational on 2011-05-25, 45 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3581.
Novarly Parcel · official public data, read properly · parcel.novarly.com