Errol Estate

Errol Estate is an operational 13 MW solar farm in Perth and Kinross, generating since 19 March 2016. Planning permission was granted on 12 June 2014, 3 months after submission. Operator of record: Elgin Energy EsCo.

13 MW
Capacity
as recorded in REPD
Operational
Status
since 19 March 2016
Solar Photovoltaics
Technology
Elgin Energy EsCo
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted17 March 2014
Permission granted12 June 2014
3 months after submission
Operational19 March 2016
21 months after consent

Screening a site of your own?

RedlineUK · £39

Perth and Kinross approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Errol Estate’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Perth and Kinross’s record on solar

Perth and Kinross has decided 22 solar farms and approved 82%, taking a median of 3.3 months. See every solar farm decision in Perth and Kinross

Other built sites within 15 km

SiteMWDistance
Battery · Operational
492.6 km
Solar Photovoltaics · Operational
0.46.9 km
Solar Photovoltaics · Operational
0.37.1 km
Battery · Operational
7.1 km
Landfill Gas · Operational
1.97.3 km
Anaerobic Digestion · Operational
1.57.5 km
Wind Onshore · Operational
107.6 km
EfW Incineration · Under Construction
7.38.4 km

How big is Errol Estate?

Errol Estate has a recorded installed capacity of 13 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Errol Estate?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Errol Estate approved and built?

The application was submitted on 17 March 2014. Permission was granted on 12 June 2014, 3 months later. The site became operational on 19 March 2016, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1930.