Errol Estate
Errol Estate is operational in Perth and Kinross with a recorded capacity of 13 MW, and has been generating since 2016-03-19.
Planning and build timeline
| Application submitted | 2014-03-17 |
| Permission granted | 2014-06-12 3 months after submission |
| Operational | 2016-03-19 21 months after consent |
Perth and Kinross’s record on solar
Perth and Kinross has decided 22 solar farms and approved 82%, taking a median of 3.3 months. See every solar farm decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Jamesfield Organic Centre - Battery Storage Battery · Operational | 49 | 2.6 km |
Perth Wastewater Treatment Works Solar Photovoltaics · Operational | 0.4 | 6.9 km |
Perth Wastewater Treatment Works (Extension) Solar Photovoltaics · Operational | 0.3 | 7.1 km |
Perth Wastewater Treatment Works (Extension) Battery · Operational | — | 7.1 km |
Binn Landfill Landfill Gas · Operational | 1.9 | 7.3 km |
Binn Farm AD (extension) Anaerobic Digestion · Operational | 1.5 | 7.5 km |
Binn Eco Park - Wind Farm Wind Onshore · Operational | 10 | 7.6 km |
Binn Eco Park - EfW EfW Incineration · Under Construction | 7.3 | 8.4 km |
How big is Errol Estate?
Errol Estate has a recorded installed capacity of 13 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Errol Estate?
REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Errol Estate approved and built?
The application was submitted on 2014-03-17. Permission was granted on 2014-06-12, 3 months later. The site became operational on 2016-03-19, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1930.