Novarly ParcelRenewable sites

Renewable sitesBinn Farm AD (extension)

Binn Farm AD (extension)

Binn Farm AD (extension) is operational in Perth and Kinross with a recorded capacity of 1.5 MW, and has been generating since 2018-04-20.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-04-20
Anaerobic Digestion
Technology
Earnside Energy
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted2015-12-07
Permission granted2016-01-27
2 months after submission
Operational2018-04-20
27 months after consent

Other built sites within 15 km

SiteMWDistance
Binn Landfill
Landfill Gas · Operational
1.90.2 km
Binn Eco Park - Wind Farm
Wind Onshore · Operational
100.5 km
Binn Eco Park - EfW
EfW Incineration · Under Construction
7.30.9 km
Jamesfield Organic Centre - Battery Storage
Battery · Operational
494.9 km
Lochelbank Wind Farm II
Wind Onshore · Operational
9.66 km
Errol Estate
Solar Photovoltaics · Operational
137.5 km
Perth Wastewater Treatment Works
Solar Photovoltaics · Operational
0.48.8 km
Perth Wastewater Treatment Works (Extension)
Solar Photovoltaics · Operational
0.38.8 km

How big is Binn Farm AD (extension)?

Binn Farm AD (extension) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Binn Farm AD (extension)?

REPD records the operator as Earnside Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Binn Farm AD (extension) approved and built?

The application was submitted on 2015-12-07. Permission was granted on 2016-01-27, 2 months later. The site became operational on 2018-04-20, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5951.

Novarly Parcel · official public data, read properly · parcel.novarly.com