Renewable sites › Hutton Battery Storage (Lower Road)
Hutton Battery Storage (Lower Road)
Hutton Battery Storage (Lower Road) is operational in Brentwood with a recorded capacity of 10 MW, and has been generating since 2020-04-01.
Planning and build timeline
| Application submitted | 2017-09-29 |
| Permission granted | 2017-12-15 3 months after submission |
| Operational | 2020-04-01 28 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crouch Solar Farm Battery · Operational | 49.9 | 5.5 km |
Crouch Solar Farm Solar Photovoltaics · Operational | 49.9 | 5.5 km |
Outwood Farm (Phase 1) Solar Photovoltaics · Operational | 5 | 6.4 km |
Ford Research And Engineering Centre, Dunton - Solar Farm Solar Photovoltaics · Operational | 5.2 | 7.1 km |
Crays Hall Farm - Solar Arrays Solar Photovoltaics · Under Construction | 25.6 | 8.2 km |
Lower Dunton Road Battery Storage Facility Battery · Operational | 28 | 8.3 km |
Fairwind Farm Solar Photovoltaics · Operational | 10 | 8.5 km |
Ongar Landfill Scheme Landfill Gas · Operational | 1 | 9.5 km |
How big is Hutton Battery Storage (Lower Road)?
Hutton Battery Storage (Lower Road) has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hutton Battery Storage (Lower Road)?
REPD records the operator as Gore Street Capital / Flexitricity Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hutton Battery Storage (Lower Road) approved and built?
The application was submitted on 2017-09-29. Permission was granted on 2017-12-15, 3 months later. The site became operational on 2020-04-01, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20396.