Worsted Farm

Worsted Farm is an operational 5 MW solar farm in Mid Sussex, generating since 16 April 2019. Planning permission was granted on 21 November 2016, 14 months after submission. Operator of record: S4N Worsted/.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 16 April 2019
Solar Photovoltaics
Technology
S4N Worsted/
Mid Sussex
Authority
England

Planning and build timeline

Application submitted15 September 2015
Permission granted21 November 2016
14 months after submission
Operational16 April 2019
29 months after consent

Screening a site of your own?

RedlineUK · £39

Mid Sussex approves 91% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Worsted Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Mid Sussex’s record on solar

Mid Sussex has decided 11 solar farms and approved 91%, taking a median of 3.6 months. See every solar farm decision in Mid Sussex

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.18.8 km
Solar Photovoltaics · Operational
0.1912.3 km
Battery · Under Construction
13.5 km

How big is Worsted Farm?

Worsted Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Worsted Farm?

REPD records the operator as S4N Worsted/. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Worsted Farm approved and built?

The application was submitted on 15 September 2015. Permission was granted on 21 November 2016, 14 months later. The site became operational on 16 April 2019, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5633.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode