Worsted Farm

Worsted Farm is operational in Mid Sussex with a recorded capacity of 5 MW, and has been generating since 2019-04-16.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2019-04-16
Solar Photovoltaics
Technology
S4N Worsted/
Mid Sussex
Authority
England

Planning and build timeline

Application submitted2015-09-15
Permission granted2016-11-21
14 months after submission
Operational2019-04-16
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Mid Sussex’s record on solar

Mid Sussex has decided 11 solar farms and approved 91%, taking a median of 3.6 months. See every solar farm decision in Mid Sussex

Other built sites within 15 km

SiteMWDistance
Majors Hill/Turners Hill Solar Farm
Solar Photovoltaics · Operational
1.18.8 km
Oriel High School
Solar Photovoltaics · Operational
0.1912.3 km
South Terminal Car Park Forecourt - Electric Vehicle Charging Forecourt
Battery · Under Construction
13.5 km

How big is Worsted Farm?

Worsted Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Worsted Farm?

REPD records the operator as S4N Worsted/. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Worsted Farm approved and built?

The application was submitted on 2015-09-15. Permission was granted on 2016-11-21, 14 months later. The site became operational on 2019-04-16, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5633.