Novarly ParcelRenewable sites

Renewable sitesOatslie Landfill Gas

Oatslie Landfill Gas

Oatslie Landfill Gas is an operational 2 MW landfill gas site in Midlothian, generating since 1 December 2006. Planning permission was granted on 10 January 2005, 4 months after submission. Operator of record: Waste Recycling Group.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2006
Landfill Gas
Technology
Waste Recycling Group
Midlothian
Authority
Scotland

Planning and build timeline

Application submitted1 September 2004
Permission granted10 January 2005
4 months after submission
Operational1 December 2006
23 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Midlothian: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Oatslie Landfill Gas’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
32.4 km
Landfill Gas · Operational
2.24.2 km
Landfill Gas · Operational
26.2 km
EfW Incineration · Operational
12.59.1 km
Anaerobic Digestion · Operational
1.59.3 km
Solar Photovoltaics · Operational
0.210.8 km
Wind Onshore · Operational
613.7 km
Landfill Gas · Operational
2.414.8 km

How big is Oatslie Landfill Gas?

Oatslie Landfill Gas has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Oatslie Landfill Gas?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Oatslie Landfill Gas approved and built?

The application was submitted on 1 September 2004. Permission was granted on 10 January 2005, 4 months later. The site became operational on 1 December 2006, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 675.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode