Renewable sites › Bonnyrigg
Bonnyrigg
Bonnyrigg is operational in Midlothian with a recorded capacity of 2.2 MW, and has been generating since 2001-07-15.
Planning and build timeline
| Application submitted | 2000-02-10 |
| Permission granted | 2000-03-29 2 months after submission |
| Operational | 2001-07-15 16 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Drummond Moor Landfill Landfill Gas · Operational | 2 | 3 km |
Oatslie Landfill Gas Landfill Gas · Operational | 2 | 4.2 km |
Easter Bush Solar Photovoltaics · Under Construction | 3 | 4.8 km |
Millerhill EfW EfW Incineration · Operational | 12.5 | 4.9 km |
Millerhill AD (Waste AD) Anaerobic Digestion · Operational | 1.5 | 5.1 km |
City of Edinburgh Council Buildings Solar Photovoltaics · Operational | 0.2 | 8.1 km |
How big is Bonnyrigg?
Bonnyrigg has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bonnyrigg?
REPD records the operator as Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bonnyrigg approved and built?
The application was submitted on 2000-02-10. Permission was granted on 2000-03-29, 2 months later. The site became operational on 2001-07-15, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 747.