Bonnyrigg

Bonnyrigg is an operational 2.2 MW landfill gas site in Midlothian, generating since 15 July 2001. Planning permission was granted on 29 March 2000, 2 months after submission. Operator of record: Natural Power.

2.2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 July 2001
Landfill Gas
Technology
Natural Power
Midlothian
Authority
Scotland

Planning and build timeline

Application submitted10 February 2000
Permission granted29 March 2000
2 months after submission
Operational15 July 2001
16 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Midlothian: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bonnyrigg’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
23 km
Landfill Gas · Operational
24.2 km
Solar Photovoltaics · Under Construction
34.8 km
EfW Incineration · Operational
12.54.9 km
Anaerobic Digestion · Operational
1.55.1 km
Solar Photovoltaics · Operational
0.28.1 km

How big is Bonnyrigg?

Bonnyrigg has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bonnyrigg?

REPD records the operator as Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bonnyrigg approved and built?

The application was submitted on 10 February 2000. Permission was granted on 29 March 2000, 2 months later. The site became operational on 15 July 2001, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 747.