Millerhill EfW

Millerhill EfW is an operational 12.5 MW energy-from-waste plant in Midlothian, generating since 1 May 2019. Planning permission was granted on 17 September 2015, 6 months after submission. Operator of record: FCC Environment.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2019
EfW Incineration
Technology
FCC Environment
Midlothian
Authority
Scotland

Planning and build timeline

Application submitted31 March 2015
Permission granted17 September 2015
6 months after submission
Operational1 May 2019
43 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Midlothian: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Millerhill EfW’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.50.2 km
Landfill Gas · Operational
24.6 km
Landfill Gas · Operational
2.24.9 km
Solar Photovoltaics · Operational
0.27 km
Landfill Gas · Operational
29.1 km
Solar Photovoltaics · Under Construction
39.3 km

How big is Millerhill EfW?

Millerhill EfW has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Millerhill EfW?

REPD records the operator as FCC Environment. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Millerhill EfW approved and built?

The application was submitted on 31 March 2015. Permission was granted on 17 September 2015, 6 months later. The site became operational on 1 May 2019, 43 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5247.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode