Drummond Moor Landfill

Drummond Moor Landfill is an operational 2 MW landfill gas site in Midlothian, generating since 1 April 2005. Planning permission was granted on 22 December 2004, 2 months after submission. Operator of record: Waste Recycling Group.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2005
Landfill Gas
Technology
Waste Recycling Group
Midlothian
Authority
Scotland

Planning and build timeline

Application submitted18 October 2004
Permission granted22 December 2004
2 months after submission
Operational1 April 2005
3 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Midlothian: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Drummond Moor Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.23 km
EfW Incineration · Operational
12.54.6 km
Anaerobic Digestion · Operational
1.54.8 km
Landfill Gas · Operational
26.2 km
Solar Photovoltaics · Under Construction
37.6 km
Solar Photovoltaics · Operational
0.210.2 km
Wind Onshore · Operational
613.6 km

How big is Drummond Moor Landfill?

Drummond Moor Landfill has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Drummond Moor Landfill?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Drummond Moor Landfill approved and built?

The application was submitted on 18 October 2004. Permission was granted on 22 December 2004, 2 months later. The site became operational on 1 April 2005, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 799.