Novarly ParcelRenewable sites

Renewable sitesEaster Bush

Easter Bush

Easter Bush is a 3 MW solar farm under construction in Midlothian. Planning permission was granted on 22 October 2021, 33 months after submission. Operator of record: University of Edinburgh (Estates Department).

3 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
University of Edinburgh (Estates Department)
Midlothian
Authority
Scotland

Planning and build timeline

Application submitted11 January 2019
Permission granted22 October 2021
33 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Midlothian approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Easter Bush’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Midlothian’s record on solar

Midlothian has decided 7 solar farms and approved 100%, taking a median of 2 months. See every solar farm decision in Midlothian

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
22.4 km
Landfill Gas · Operational
2.24.8 km
Landfill Gas · Operational
27.6 km
EfW Incineration · Operational
12.59.3 km
Solar Photovoltaics · Operational
0.29.3 km
Anaerobic Digestion · Operational
1.59.5 km
Landfill Gas · Operational
2.412.6 km

How big is Easter Bush?

Easter Bush has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Easter Bush?

REPD records the operator as University of Edinburgh (Estates Department). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Easter Bush approved and built?

The application was submitted on 11 January 2019. Permission was granted on 22 October 2021, 33 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7222.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode