Oak Grove Farm is an operational 5.7 MW solar farm in Monmouthshire, generating since 30 March 2017. REPD does not record the planning grant date. Operator of record: Monmouthshire County Council.

5.7 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2017
Solar Photovoltaics
Technology
Monmouthshire County Council
Monmouthshire
Authority
Wales

Planning and build timeline

Application submitted5 March 2015
Permission grantednot recorded
Operational30 March 2017

Screening a site of your own?

RedlineUK · £39

Monmouthshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Oak Grove Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Monmouthshire’s record on solar

Monmouthshire has decided 10 solar farms and approved 100%, taking a median of 4.4 months. See every solar farm decision in Monmouthshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
52.6 km
Solar Photovoltaics · Operational
62.7 km
Solar Photovoltaics · Operational
55.5 km
Solar Photovoltaics · Operational
56.1 km
Solar Photovoltaics · Operational
3.57 km
Wind Onshore · Operational
58.7 km
Wind Onshore · Operational
4.28.7 km
EfW Incineration · Operational
329 km

How big is Oak Grove Farm?

Oak Grove Farm has a recorded installed capacity of 5.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Oak Grove Farm?

REPD records the operator as Monmouthshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Oak Grove Farm approved and built?

The application was submitted on 5 March 2015. REPD does not record a grant date. The site became operational on 30 March 2017.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6493.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode