Land adjacent to Church Road

Land adjacent to Church Road is an operational 3.5 MW solar farm in South Gloucestershire, generating since 31 March 2016. Planning permission was granted on 1 September 2015, 5 months after submission. Operator of record: Canadian Solar.

3.5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2016
Solar Photovoltaics
Technology
Canadian Solar
South Gloucestershire
Authority
England

Planning and build timeline

Application submitted13 April 2015
Permission granted1 September 2015
5 months after submission
Operational31 March 2016
7 months after consent

Screening a site of your own?

RedlineUK · £39

South Gloucestershire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land adjacent to Church Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Gloucestershire’s record on solar

South Gloucestershire has decided 54 solar farms and approved 96%, taking a median of 1.8 months. See every solar farm decision in South Gloucestershire

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Operational
322.3 km
Wind Onshore · Operational
52.8 km
Wind Onshore · Operational
4.22.8 km
Solar Photovoltaics · Operational
1.83.3 km
EfW Incineration · Operational
343.6 km
Battery · Operational
324.8 km
Solar Photovoltaics · Operational
1.85.2 km
Solar Photovoltaics · Under Construction
3.815.2 km

How big is Land adjacent to Church Road?

Land adjacent to Church Road has a recorded installed capacity of 3.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land adjacent to Church Road?

REPD records the operator as Canadian Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land adjacent to Church Road approved and built?

The application was submitted on 13 April 2015. Permission was granted on 1 September 2015, 5 months later. The site became operational on 31 March 2016, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5207.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode