Renewable sites › Great Knowle Farm Solar
Great Knowle Farm Solar
Great Knowle Farm Solar is an operational 3 MW solar farm in Torridge, generating since 27 July 2012. Planning permission was granted on 23 June 2011, 3 months after submission. Operator of record: The Green Company.
Planning and build timeline
| Application submitted | 4 April 2011 |
| Permission granted | 23 June 2011 3 months after submission |
| Operational | 27 July 2012 13 months after consent |
Screening a site of your own?
Torridge approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Great Knowle Farm Solar’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on solar
Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 11.8 | 0.7 km |
Solar Photovoltaics · Operational | 4.2 | 2.2 km |
Solar Photovoltaics · Operational | 6.7 | 2.3 km |
Anaerobic Digestion · Operational | 1.4 | 3.2 km |
Solar Photovoltaics · Operational | 42 | 3.4 km |
Solar Photovoltaics · Operational | 15.6 | 4 km |
Solar Photovoltaics · Operational | 3.6 | 4.5 km |
Solar Photovoltaics · Operational | 5.3 | 5.3 km |
How big is Great Knowle Farm Solar?
Great Knowle Farm Solar has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Great Knowle Farm Solar?
REPD records the operator as The Green Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Great Knowle Farm Solar approved and built?
The application was submitted on 4 April 2011. Permission was granted on 23 June 2011, 3 months later. The site became operational on 27 July 2012, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1549.