Renewable sites › Great Knowle Farm Solar
Great Knowle Farm Solar
Great Knowle Farm Solar is operational in Torridge with a recorded capacity of 3 MW, and has been generating since 2012-07-27.
Planning and build timeline
| Application submitted | 2011-04-04 |
| Permission granted | 2011-06-23 3 months after submission |
| Operational | 2012-07-27 13 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on solar
Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Derriton Fields Solar Farm Solar Photovoltaics · Operational | 11.8 | 0.7 km |
Land West of Parsonage Wood Solar Photovoltaics · Operational | 4.2 | 2.2 km |
CRINACOTT SOLAR FARM (Pyworthy) Solar Photovoltaics · Operational | 6.7 | 2.3 km |
North Tamar Environ Project - Holsworthy (Farm AD) Anaerobic Digestion · Operational | 1.4 | 3.2 km |
Derril Water Solar Farm - Solar Farm Solar Photovoltaics · Operational | 42 | 3.4 km |
Pitworthy Farm Solar Park Solar Photovoltaics · Operational | 15.6 | 4 km |
EASTACOMBE SOLAR FARM Solar Photovoltaics · Operational | 3.6 | 4.5 km |
Bradford Solar Park Solar Photovoltaics · Operational | 5.3 | 5.3 km |
How big is Great Knowle Farm Solar?
Great Knowle Farm Solar has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Great Knowle Farm Solar?
REPD records the operator as The Green Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Great Knowle Farm Solar approved and built?
The application was submitted on 2011-04-04. Permission was granted on 2011-06-23, 3 months later. The site became operational on 2012-07-27, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1549.
Novarly Parcel · official public data, read properly · parcel.novarly.com