Land West of Parsonage Wood is an operational 4.2 MW solar farm in Torridge, generating since 31 January 2016. Planning permission was granted on 30 September 2015, 2 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 5 August 2015 |
| Permission granted | 30 September 2015 2 months after submission |
| Operational | 31 January 2016 4 months after consent |
Screening a site of your own?
Torridge approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land West of Parsonage Wood’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on solar
Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 6.7 | 0.2 km |
Solar Photovoltaics · Operational | 42 | 1.5 km |
Solar Photovoltaics · Operational | 3 | 2.2 km |
Solar Photovoltaics · Operational | 11.8 | 2.6 km |
Solar Photovoltaics · Operational | 5.3 | 3.2 km |
Solar Photovoltaics · Operational | 15.6 | 4 km |
Solar Photovoltaics · Operational | 3.6 | 4.9 km |
Anaerobic Digestion · Operational | 1.4 | 5.4 km |
How big is Land West of Parsonage Wood?
Land West of Parsonage Wood has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land West of Parsonage Wood?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land West of Parsonage Wood approved and built?
The application was submitted on 5 August 2015. Permission was granted on 30 September 2015, 2 months later. The site became operational on 31 January 2016, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5582.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode