Land West of Parsonage Wood is operational in Torridge with a recorded capacity of 4.2 MW, and has been generating since 2016-01-31.

4.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-01-31
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Torridge
Authority
England

Planning and build timeline

Application submitted2015-08-05
Permission granted2015-09-30
2 months after submission
Operational2016-01-31
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on solar

Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge

Other built sites within 15 km

SiteMWDistance
CRINACOTT SOLAR FARM (Pyworthy)
Solar Photovoltaics · Operational
6.70.2 km
Derril Water Solar Farm - Solar Farm
Solar Photovoltaics · Operational
421.5 km
Great Knowle Farm Solar
Solar Photovoltaics · Operational
32.2 km
Derriton Fields Solar Farm
Solar Photovoltaics · Operational
11.82.6 km
Bradford Solar Park
Solar Photovoltaics · Operational
5.33.2 km
Pitworthy Farm Solar Park
Solar Photovoltaics · Operational
15.64 km
EASTACOMBE SOLAR FARM
Solar Photovoltaics · Operational
3.64.9 km
North Tamar Environ Project - Holsworthy (Farm AD)
Anaerobic Digestion · Operational
1.45.4 km

How big is Land West of Parsonage Wood?

Land West of Parsonage Wood has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land West of Parsonage Wood?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land West of Parsonage Wood approved and built?

The application was submitted on 2015-08-05. Permission was granted on 2015-09-30, 2 months later. The site became operational on 2016-01-31, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5582.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council