Renewable sites › CRINACOTT SOLAR FARM (Pyworthy)
CRINACOTT SOLAR FARM (Pyworthy)
CRINACOTT SOLAR FARM (Pyworthy) is operational in Torridge with a recorded capacity of 6.7 MW, and has been generating since 2013-03-31.
Planning and build timeline
| Application submitted | 2012-10-18 |
| Permission granted | 2013-01-17 3 months after submission |
| Operational | 2013-03-31 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on solar
Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land West of Parsonage Wood Solar Photovoltaics · Operational | 4.2 | 0.2 km |
Derril Water Solar Farm - Solar Farm Solar Photovoltaics · Operational | 42 | 1.3 km |
Great Knowle Farm Solar Solar Photovoltaics · Operational | 3 | 2.3 km |
Derriton Fields Solar Farm Solar Photovoltaics · Operational | 11.8 | 2.7 km |
Bradford Solar Park Solar Photovoltaics · Operational | 5.3 | 3 km |
Pitworthy Farm Solar Park Solar Photovoltaics · Operational | 15.6 | 3.9 km |
EASTACOMBE SOLAR FARM Solar Photovoltaics · Operational | 3.6 | 5.1 km |
North Tamar Environ Project - Holsworthy (Farm AD) Anaerobic Digestion · Operational | 1.4 | 5.4 km |
How big is CRINACOTT SOLAR FARM (Pyworthy)?
CRINACOTT SOLAR FARM (Pyworthy) has a recorded installed capacity of 6.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates CRINACOTT SOLAR FARM (Pyworthy)?
REPD records the operator as Sunsave 4 Ltd/ Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was CRINACOTT SOLAR FARM (Pyworthy) approved and built?
The application was submitted on 2012-10-18. Permission was granted on 2013-01-17, 3 months later. The site became operational on 2013-03-31, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1094.