Novarly ParcelRenewable sites

Renewable sitesNevis Range

Nevis Range

Nevis Range is operational in Highland with a recorded capacity of 1.1 MW, and has been generating since 2017-03-16.

1.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-16
Small Hydro
Technology
Nevis Range Development Company
Highland
Authority
Scotland

Planning and build timeline

Application submitted2014-08-13
Permission granted2014-12-16
4 months after submission
Operational2017-03-16
27 months after consent

Other built sites within 15 km

SiteMWDistance
Mucomir
Small Hydro · Operational
27.5 km
Lochaber
Large Hydro · Operational
658 km
Lochaber High School (Resubmission)
Solar Photovoltaics · Operational
0.38.2 km
Derrydarroch
Small Hydro · Operational
1.98.4 km
Cia Aig Hydro
Small Hydro · Operational
312.5 km
Abhainn Gleann Nam Fiadh
Small Hydro · Operational
212.8 km
Loch Eilde Mor Hydro (Kinlochleven extension)
Small Hydro · Operational
213.2 km
Kinlochleven Hydro Power Station
Large Hydro · Operational
19.514.8 km

How big is Nevis Range?

Nevis Range has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nevis Range?

REPD records the operator as Nevis Range Development Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nevis Range approved and built?

The application was submitted on 2014-08-13. Permission was granted on 2014-12-16, 4 months later. The site became operational on 2017-03-16, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 496.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council