Nevis Range is an operational 1.1 MW hydro scheme in Highland, generating since 16 March 2017. Planning permission was granted on 16 December 2014, 4 months after submission. Operator of record: Nevis Range Development Company.
Planning and build timeline
| Application submitted | 13 August 2014 |
| Permission granted | 16 December 2014 4 months after submission |
| Operational | 16 March 2017 27 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Nevis Range’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 2 | 7.5 km |
Large Hydro · Operational | 65 | 8 km |
Solar Photovoltaics · Operational | 0.3 | 8.2 km |
Small Hydro · Operational | 1.9 | 8.4 km |
Small Hydro · Operational | 3 | 12.5 km |
Small Hydro · Operational | 2 | 12.8 km |
Small Hydro · Operational | 2 | 13.2 km |
Large Hydro · Operational | 19.5 | 14.8 km |
How big is Nevis Range?
Nevis Range has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nevis Range?
REPD records the operator as Nevis Range Development Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nevis Range approved and built?
The application was submitted on 13 August 2014. Permission was granted on 16 December 2014, 4 months later. The site became operational on 16 March 2017, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 496.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode