Novarly ParcelRenewable sites

Renewable sitesLoch Eilde Mor Hydro (Kinlochleven extension)

Loch Eilde Mor Hydro (Kinlochleven extension)

Loch Eilde Mor Hydro (Kinlochleven extension) is an operational 2 MW hydro scheme in Scotland, generating since 6 October 2017. Planning permission was granted on 22 July 2011, 43 months after submission. Operator of record: Green Highland Renewables.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 6 October 2017
Small Hydro
Technology
Green Highland Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted3 January 2008
Permission granted22 July 2011
43 months after submission
Operational6 October 2017
75 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Loch Eilde Mor Hydro (Kinlochleven extension)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Large Hydro · Operational
19.53.3 km
Small Hydro · Operational
210.8 km
Small Hydro · Under Construction
1.412.7 km
Small Hydro · Operational
1.113.2 km
Large Hydro · Operational
6514.6 km

How big is Loch Eilde Mor Hydro (Kinlochleven extension)?

Loch Eilde Mor Hydro (Kinlochleven extension) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Loch Eilde Mor Hydro (Kinlochleven extension)?

REPD records the operator as Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Loch Eilde Mor Hydro (Kinlochleven extension) approved and built?

The application was submitted on 3 January 2008. Permission was granted on 22 July 2011, 43 months later. The site became operational on 6 October 2017, 75 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 410.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode