Renewable sites › Abhainn Gleann Nam Fiadh
Abhainn Gleann Nam Fiadh
Abhainn Gleann Nam Fiadh is operational in Highland with a recorded capacity of 2 MW, and has been generating since 2017-08-01.
Planning and build timeline
| Application submitted | 2014-08-28 |
| Permission granted | 2014-12-22 4 months after submission |
| Operational | 2017-08-01 31 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Loch Eilde Mor Hydro (Kinlochleven extension) Small Hydro · Operational | 2 | 10.8 km |
Nevis Range Small Hydro · Operational | 1.1 | 12.8 km |
Kinlochleven Hydro Power Station Large Hydro · Operational | 19.5 | 14.1 km |
How big is Abhainn Gleann Nam Fiadh?
Abhainn Gleann Nam Fiadh has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Abhainn Gleann Nam Fiadh?
REPD records the operator as Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Abhainn Gleann Nam Fiadh approved and built?
The application was submitted on 2014-08-28. Permission was granted on 2014-12-22, 4 months later. The site became operational on 2017-08-01, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 498.
Novarly Parcel · official public data, read properly · parcel.novarly.com