Lochaber High School (Resubmission)
Lochaber High School (Resubmission) is operational in Highland with a recorded capacity of 0.3 MW, and has been generating since 2019-12-01.
Planning and build timeline
| Application submitted | 2019-06-13 |
| Permission granted | 2019-08-16 2 months after submission |
| Operational | 2019-12-01 4 months after consent |
Highland’s record on solar
Highland has decided 13 solar farms and approved 100%, taking a median of 2 months. See every solar farm decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Derrydarroch Small Hydro · Operational | 1.9 | 0.5 km |
Lochaber Large Hydro · Operational | 65 | 0.9 km |
Nevis Range Small Hydro · Operational | 1.1 | 8.2 km |
Mucomir Small Hydro · Operational | 2 | 10 km |
Cia Aig Hydro Small Hydro · Operational | 3 | 13.7 km |
How big is Lochaber High School (Resubmission)?
Lochaber High School (Resubmission) has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lochaber High School (Resubmission)?
REPD records the operator as Highland Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lochaber High School (Resubmission) approved and built?
The application was submitted on 2019-06-13. Permission was granted on 2019-08-16, 2 months later. The site became operational on 2019-12-01, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7281.