Renewable sites › Derrydarroch
Derrydarroch
Derrydarroch is operational in Scottish Government (S36) with a recorded capacity of 1.9 MW, and has been generating since 2015-12-15.
Planning and build timeline
| Application submitted | 2009-07-21 |
| Permission granted | 2010-04-24 9 months after submission |
| Operational | 2015-12-15 68 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lochaber High School (Resubmission) Solar Photovoltaics · Operational | 0.3 | 0.5 km |
Lochaber Large Hydro · Operational | 65 | 0.6 km |
Nevis Range Small Hydro · Operational | 1.1 | 8.4 km |
Mucomir Small Hydro · Operational | 2 | 10.5 km |
Cia Aig Hydro Small Hydro · Operational | 3 | 14.2 km |
Kinlochleven Hydro Power Station Large Hydro · Operational | 19.5 | 14.9 km |
How big is Derrydarroch?
Derrydarroch has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Derrydarroch?
REPD records the operator as Darroch Power Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Derrydarroch approved and built?
The application was submitted on 2009-07-21. Permission was granted on 2010-04-24, 9 months later. The site became operational on 2015-12-15, 68 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 474.