Novarly ParcelRenewable sites

Renewable sitesNEILSTON WIND FARM

NEILSTON WIND FARM

NEILSTON WIND FARM is an operational 9.2 MW onshore wind farm in East Renfrewshire, generating since 13 May 2013. Planning permission was granted on 16 May 2011, 18 months after submission. Operator of record: Renewables Infrastructure Group.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 13 May 2013
Wind Onshore
Technology
Renewables Infrastructure Group
East Renfrewshire
Authority
Scotland

Planning and build timeline

Application submitted19 November 2009
Permission granted16 May 2011
18 months after submission
Operational13 May 2013
24 months after consent

Screening a site of your own?

RedlineUK · £39

East Renfrewshire approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with NEILSTON WIND FARM’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

East Renfrewshire’s record on onshore wind

East Renfrewshire has decided 10 onshore wind schemes and approved 80%, taking a median of 19.6 months. See every onshore wind scheme decision in East Renfrewshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.42.5 km
Wind Onshore · Operational
128.1 km
Battery · Under Construction
5010.5 km
Battery · Under Construction
12.4 km
Solar Photovoltaics · Under Construction
19.912.4 km
Wind Onshore · Under Construction
4513.2 km
Wind Onshore · Operational
4.713.5 km
Wind Onshore · Operational
1.813.7 km

How big is NEILSTON WIND FARM?

NEILSTON WIND FARM has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates NEILSTON WIND FARM?

REPD records the operator as Renewables Infrastructure Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was NEILSTON WIND FARM approved and built?

The application was submitted on 19 November 2009. Permission was granted on 16 May 2011, 18 months later. The site became operational on 13 May 2013, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3857.