NEILSTON WIND FARM is an operational 9.2 MW onshore wind farm in East Renfrewshire, generating since 13 May 2013. Planning permission was granted on 16 May 2011, 18 months after submission. Operator of record: Renewables Infrastructure Group.
Planning and build timeline
| Application submitted | 19 November 2009 |
| Permission granted | 16 May 2011 18 months after submission |
| Operational | 13 May 2013 24 months after consent |
Screening a site of your own?
East Renfrewshire approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with NEILSTON WIND FARM’s recorded coordinate — swap in your own postcode or coordinates.
East Renfrewshire’s record on onshore wind
East Renfrewshire has decided 10 onshore wind schemes and approved 80%, taking a median of 19.6 months. See every onshore wind scheme decision in East Renfrewshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 2.4 | 2.5 km |
Wind Onshore · Operational | 12 | 8.1 km |
Battery · Under Construction | 50 | 10.5 km |
Battery · Under Construction | — | 12.4 km |
Solar Photovoltaics · Under Construction | 19.9 | 12.4 km |
Wind Onshore · Under Construction | 45 | 13.2 km |
Wind Onshore · Operational | 4.7 | 13.5 km |
Wind Onshore · Operational | 1.8 | 13.7 km |
How big is NEILSTON WIND FARM?
NEILSTON WIND FARM has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates NEILSTON WIND FARM?
REPD records the operator as Renewables Infrastructure Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was NEILSTON WIND FARM approved and built?
The application was submitted on 19 November 2009. Permission was granted on 16 May 2011, 18 months later. The site became operational on 13 May 2013, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3857.