Novarly ParcelRenewable sites

Renewable sitesNeilston Greener Grid Park

Neilston Greener Grid Park

Neilston Greener Grid Park is a 50 MW battery storage site under construction in Renfrewshire. Planning permission was granted on 28 April 2022, 15 months after submission. Operator of record: Statkraft UK LTD.

50 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Statkraft UK LTD
Renfrewshire
Authority
Scotland

Planning and build timeline

Application submitted21 January 2021
Permission granted28 April 2022
15 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Renfrewshire approves 83% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Neilston Greener Grid Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Renfrewshire’s record on battery storage

Renfrewshire has decided 6 battery storage schemes and approved 83%, taking a median of 4.9 months. See every battery storage scheme decision in Renfrewshire

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
2 km
Solar Photovoltaics · Under Construction
19.92 km
EfW Incineration · Under Construction
454.8 km
Solar Photovoltaics · Operational
0.189.1 km
Wind Onshore · Operational
129.4 km
EfW Incineration · Operational
10.3 km
Wind Onshore · Operational
9.210.5 km
Anaerobic Digestion · Operational
511.5 km

How big is Neilston Greener Grid Park?

Neilston Greener Grid Park has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Neilston Greener Grid Park?

REPD records the operator as Statkraft UK LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Neilston Greener Grid Park approved and built?

The application was submitted on 21 January 2021. Permission was granted on 28 April 2022, 15 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8830.