Novarly ParcelRenewable planning

Renewable planning SolarLeicester

Solar planning in Leicester

Leicester has decided 13 solar farms and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 8 MW. 3 applications still awaiting a decision.

100%
Approved
13 granted · 0 refused
1.8 mo
Median decision
UK 2.3 mo
8 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Leicester compares

Against the 298 UK authorities with 5+ solar decisions, Leicester sits in the 77th percentile for approval rate (7 points above the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2019)119Approved — 1 (2022)122Approved — 3 (2023)323Approved — 4 (2024)424Approved — 3 (2025)325
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (17)

SchemeMWStatusDecided
Rushey Mead Academy, Melton Road - Solar Panels
eEnergy Group Plc · 20260101
0.28Application Submitted2026-01-27
Orchard Mead Academy, Keyham Lane West - Solar Panels
eEnergy Group Plc · 20260096
0.28Application Submitted2026-01-27
Gateway College, Colin Grundy Drive - Solar Panels
Gateway College · 20251613 · 1.6 mo to decide
0.15Awaiting Construction2025-11-26
Sunningdale Road - Solar Panels
Harvest Green Developments · 20251031 · 1.6 mo to decide
1.57Awaiting Construction2025-08-14
Evington Leisure Centre - Solar Panels
Evington Leisure Centre · 20250115 · 0.9 mo to decide
Awaiting Construction2025-03-28
Lewisher Road - Solar Arrays
Marpatt Plc · 20241074 · 2.6 mo to decide
0.17Awaiting Construction2024-09-06
Ashton Business Park, Ashton Close - Solar Array
The Metal Works Limited · 20241081 · 1.8 mo to decide
0.18Awaiting Construction2024-08-12
Madani Schools Federation - Solar Panels
Solar Options for Schools Limited · 20240296 · 2.2 mo to decide
0.27Awaiting Construction2024-04-22
Pepsico International Limited, Leycroft Road - Solar Panels
Walkers Snacks (Distribution) Limited · 20240078 · 1.8 mo to decide
3.25Under Construction2024-03-06
Langham Road - Solar Panels
Cactus Energy · 20231726 · 2.4 mo to decide
0.17Awaiting Construction2023-11-23
Newarke St Car Park - Solar Panels
Leicester City Council
Under Construction2023-11-17
Bingo Club, Beaumont Way - Solar Panels
Buzz Group Limited · 20231458 · 1.7 mo to decide
0.4Awaiting Construction2023-09-22
Hoods Close - Solar Panels
Trelleborg Industrial AVS · 20230307
1.7Under Construction2023-04-06
First Bus Depot, Humphreys Way - Solar Panels
FirstBus · 20230167
0.18Application Submitted2023-02-13
Granby Road - Solar PV Panels & Air Source Heat Pumps
Leicester City Council · 20212827 · 3.3 mo to decide
Awaiting Construction2022-03-14
Humberstone Heights Golf Club - Solar Panels
Leicester City Council · 20212330
Application Withdrawn2022-01-14
National Space Centre
EvoEnergy · 20190026 · 2.1 mo to decide
0.2Operational2019-03-15

Does Leicester approve solar farms?

Yes — of the 13 solar farms Leicester has decided, 100% were approved (13 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Leicester?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Leicester consented?

8 MW has been consented across 13 approved schemes. A further 3 applications awaits a decision.

Other technologies in Leicester

Battery storage in LeicesterOnshore wind in Leicester

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.