Novarly ParcelRenewable sites

Renewable sitesHarborough Road Store

Harborough Road Store

Harborough Road Store is operational in Oadby and Wigston with a recorded capacity of 0.2 MW, and has been generating since 2022-01-01.

0.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-01-01
Solar Photovoltaics
Technology
Lidl UK
Oadby and Wigston
Authority
England

Planning and build timeline

Application submitted2019-12-20
Permission granted2020-04-16
4 months after submission
Operational2022-01-01
21 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Oadby and Wigston’s record on solar

Oadby and Wigston has decided 5 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Oadby and Wigston

Other built sites within 15 km

SiteMWDistance
Newarke St Car Park - Solar Panels
Solar Photovoltaics · Under Construction
5.1 km
Blaby Solar Farm
Solar Photovoltaics · Operational
3.55.1 km
Land Off Ingarsby Lane
Solar Photovoltaics · Operational
2.16.7 km
National Space Centre
Solar Photovoltaics · Operational
0.27 km
Warren Quarry Landfill Gas Scheme
Landfill Gas · Operational
1.98.7 km
Land at and adjacent to Leicester Forest Services
Battery · Operational
1.58.8 km
Enderby Warren Phase II
Landfill Gas · Operational
4.98.8 km
National Grid Enderby Substation
Battery · Operational
579.2 km

How big is Harborough Road Store?

Harborough Road Store has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harborough Road Store?

REPD records the operator as Lidl UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harborough Road Store approved and built?

The application was submitted on 2019-12-20. Permission was granted on 2020-04-16, 4 months later. The site became operational on 2022-01-01, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7819.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council