Harborough Road Store is an operational 0.2 MW solar farm in Oadby and Wigston, generating since 1 January 2022. Planning permission was granted on 16 April 2020, 4 months after submission. Operator of record: Lidl UK.

0.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2022
Solar Photovoltaics
Technology
Lidl UK
Oadby and Wigston
Authority
England

Planning and build timeline

Application submitted20 December 2019
Permission granted16 April 2020
4 months after submission
Operational1 January 2022
21 months after consent

Screening a site of your own?

RedlineUK · £39

Oadby and Wigston approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Harborough Road Store’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Oadby and Wigston’s record on solar

Oadby and Wigston has decided 5 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Oadby and Wigston

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
5.1 km
Solar Photovoltaics · Operational
3.55.1 km
Solar Photovoltaics · Operational
2.16.7 km
Solar Photovoltaics · Operational
0.27 km
Landfill Gas · Operational
1.98.7 km
Battery · Operational
1.58.8 km
Landfill Gas · Operational
4.98.8 km
Battery · Operational
579.2 km

How big is Harborough Road Store?

Harborough Road Store has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harborough Road Store?

REPD records the operator as Lidl UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harborough Road Store approved and built?

The application was submitted on 20 December 2019. Permission was granted on 16 April 2020, 4 months later. The site became operational on 1 January 2022, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7819.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode