Novarly ParcelRenewable sites

Renewable sitesNational Grid Enderby Substation

National Grid Enderby Substation

National Grid Enderby Substation is operational in Blaby with a recorded capacity of 57 MW, and has been generating since 2025-02-01.

57 MW
Capacity
as recorded in REPD
Operational
Status
since 2025-02-01
Battery
Technology
Gore Street
Blaby
Authority
England

Planning and build timeline

Application submitted2020-08-28
Permission granted2021-02-04
5 months after submission
Operational2025-02-01
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Blaby’s record on battery storage

Blaby has decided 5 battery storage schemes and approved 100%, taking a median of 5.3 months. See every battery storage scheme decision in Blaby

Other built sites within 15 km

SiteMWDistance
Enderby Warren Phase II
Landfill Gas · Operational
4.90.5 km
Warren Quarry Landfill Gas Scheme
Landfill Gas · Operational
1.90.5 km
Enderby Storage, Redcomb Farm
Battery · Operational
49.90.5 km
A C Shropshire (Farm AD)
Anaerobic Digestion · Operational
2.52.1 km
Land at and adjacent to Leicester Forest Services
Battery · Operational
1.52.3 km
Narborough Landfill
Landfill Gas · Operational
2.73 km
Kirby Road Solar Panels
Solar Photovoltaics · Under Construction
0.495.3 km
Desford Solar Farm
Solar Photovoltaics · Operational
55.4 km

How big is National Grid Enderby Substation?

National Grid Enderby Substation has a recorded installed capacity of 57 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates National Grid Enderby Substation?

REPD records the operator as Gore Street. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was National Grid Enderby Substation approved and built?

The application was submitted on 2020-08-28. Permission was granted on 2021-02-04, 5 months later. The site became operational on 2025-02-01, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8037.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council