Novarly ParcelRenewable sites

Renewable sitesWarren Quarry Landfill Gas Scheme

Warren Quarry Landfill Gas Scheme

Warren Quarry Landfill Gas Scheme is an operational 1.9 MW landfill gas site in Blaby, generating since 14 November 1998. Planning permission was granted on 25 November 1997, 4 months after submission. Operator of record: Warren Energy Ltd.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 14 November 1998
Landfill Gas
Technology
Warren Energy Ltd
Blaby
Authority
England

Planning and build timeline

Application submitted31 July 1997
Permission granted25 November 1997
4 months after submission
Operational14 November 1998
12 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Blaby: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Warren Quarry Landfill Gas Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
4.90.1 km
Battery · Operational
570.5 km
Battery · Operational
49.91 km
Anaerobic Digestion · Operational
2.52.4 km
Battery · Operational
1.52.4 km
Landfill Gas · Operational
2.73 km
Solar Photovoltaics · Under Construction
0.495.5 km
Solar Photovoltaics · Operational
55.8 km

How big is Warren Quarry Landfill Gas Scheme?

Warren Quarry Landfill Gas Scheme has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Warren Quarry Landfill Gas Scheme?

REPD records the operator as Warren Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Warren Quarry Landfill Gas Scheme approved and built?

The application was submitted on 31 July 1997. Permission was granted on 25 November 1997, 4 months later. The site became operational on 14 November 1998, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 534.

Novarly Parcel · official public data, read properly · parcel.novarly.com