Novarly ParcelRenewable sites

Renewable sitesWarren Quarry Landfill Gas Scheme

Warren Quarry Landfill Gas Scheme

Warren Quarry Landfill Gas Scheme is operational in Blaby with a recorded capacity of 1.9 MW, and has been generating since 1998-11-14.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1998-11-14
Landfill Gas
Technology
Warren Energy Ltd
Blaby
Authority
England

Planning and build timeline

Application submitted1997-07-31
Permission granted1997-11-25
4 months after submission
Operational1998-11-14
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Enderby Warren Phase II
Landfill Gas · Operational
4.90.1 km
National Grid Enderby Substation
Battery · Operational
570.5 km
Enderby Storage, Redcomb Farm
Battery · Operational
49.91 km
A C Shropshire (Farm AD)
Anaerobic Digestion · Operational
2.52.4 km
Land at and adjacent to Leicester Forest Services
Battery · Operational
1.52.4 km
Narborough Landfill
Landfill Gas · Operational
2.73 km
Kirby Road Solar Panels
Solar Photovoltaics · Under Construction
0.495.5 km
Desford Solar Farm
Solar Photovoltaics · Operational
55.8 km

How big is Warren Quarry Landfill Gas Scheme?

Warren Quarry Landfill Gas Scheme has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Warren Quarry Landfill Gas Scheme?

REPD records the operator as Warren Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Warren Quarry Landfill Gas Scheme approved and built?

The application was submitted on 1997-07-31. Permission was granted on 1997-11-25, 4 months later. The site became operational on 1998-11-14, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 534.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council