Nash Waste Water Treatment Works Turbine
Nash Waste Water Treatment Works Turbine is an operational 2.5 MW onshore wind farm in Newport, generating since 15 March 2017. Planning permission was granted on 4 July 2012, 7 months after submission. Operator of record: Welsh Water.
Planning and build timeline
| Application submitted | 8 December 2011 |
| Permission granted | 4 July 2012 7 months after submission |
| Operational | 15 March 2017 56 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Newport: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Nash Waste Water Treatment Works Turbine’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 120 | 0.7 km |
Biomass (co-firing) · Operational | 18 | 0.7 km |
Battery · Under Construction | 230 | 0.7 km |
Biomass (dedicated) · Operational | 9 | 1.1 km |
Wind Onshore · Operational | 2.3 | 1.2 km |
Wind Onshore · Operational | 5 | 1.7 km |
Battery · Operational | — | 1.8 km |
Battery · Operational | 20 | 2 km |
How big is Nash Waste Water Treatment Works Turbine?
Nash Waste Water Treatment Works Turbine has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nash Waste Water Treatment Works Turbine?
REPD records the operator as Welsh Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nash Waste Water Treatment Works Turbine approved and built?
The application was submitted on 8 December 2011. Permission was granted on 4 July 2012, 7 months later. The site became operational on 15 March 2017, 56 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3887.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode