Liberty Steel Power Station
Liberty Steel Power Station is operational in Newport with a recorded capacity of 9 MW, and has been generating since 2017-01-15.
Planning and build timeline
| Application submitted | 2016-02-01 |
| Permission granted | 2016-03-03 1 months after submission |
| Operational | 2017-01-15 10 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solutia UK Ltd Wind Onshore · Operational | 5 | 0.6 km |
Traston Road Battery · Operational | 20 | 0.8 km |
ANP Newport Wind Turbine Wind Onshore · Operational | 2.3 | 1 km |
Nash Waste Water Treatment Works Turbine Wind Onshore · Operational | 2.5 | 1.1 km |
Geraint Thomas National Velodrome - Solar Solar Photovoltaics · Operational | — | 1.5 km |
Uskmouth Power Station Biomass (co-firing) · Operational | 18 | 1.7 km |
Uskmouth Power Station - Battery Storage Battery · Under Construction | 230 | 1.7 km |
Uskmouth Power Station, West Nash Road - Battery Storage Facility Battery · Under Construction | 120 | 1.8 km |
How big is Liberty Steel Power Station?
Liberty Steel Power Station has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Liberty Steel Power Station?
REPD records the operator as SIMEC/ Liberty House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Liberty Steel Power Station approved and built?
The application was submitted on 2016-02-01. Permission was granted on 2016-03-03, 1 months later. The site became operational on 2017-01-15, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6184.