Liberty Steel Power Station

Liberty Steel Power Station is an operational 9 MW biomass plant in Newport, generating since 15 January 2017. Planning permission was granted on 3 March 2016, 1 months after submission. Operator of record: SIMEC/ Liberty House.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 15 January 2017
Biomass (dedicated)
Technology
SIMEC/ Liberty House
Newport
Authority
Wales

Planning and build timeline

Application submitted1 February 2016
Permission granted3 March 2016
1 months after submission
Operational15 January 2017
10 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Newport: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Liberty Steel Power Station’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
50.6 km
Battery · Operational
200.8 km
Wind Onshore · Operational
2.31 km
Wind Onshore · Operational
2.51.1 km
Solar Photovoltaics · Operational
1.5 km
Biomass (co-firing) · Operational
181.7 km
Battery · Under Construction
2301.7 km
Battery · Under Construction
1201.8 km

How big is Liberty Steel Power Station?

Liberty Steel Power Station has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Liberty Steel Power Station?

REPD records the operator as SIMEC/ Liberty House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Liberty Steel Power Station approved and built?

The application was submitted on 1 February 2016. Permission was granted on 3 March 2016, 1 months later. The site became operational on 15 January 2017, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6184.