Novarly ParcelRenewable sites

Renewable sitesLlanwern Solar Farm & Battery Storage

Llanwern Solar Farm & Battery Storage

Llanwern Solar Farm & Battery Storage is operational in Wales, and has been generating since 2021-03-01.

Capacity
as recorded in REPD
Operational
Status
since 2021-03-01
Battery
Technology
NextEnergy Capital LLP
National
Authority
Wales

Planning and build timeline

Application submitted2018-02-20
Permission granted2019-04-18
14 months after submission
Operational2021-03-01
22 months after consent

Welsh Government (NSIP)’s record on battery storage

Welsh Government (NSIP) has decided 15 battery storage schemes and approved 80%, taking a median of 16.7 months. See every battery storage scheme decision in Welsh Government (NSIP)

Other built sites within 15 km

SiteMWDistance
Uskmouth Power Station
Biomass (co-firing) · Operational
181.5 km
Uskmouth Power Station - Battery Storage
Battery · Under Construction
2301.5 km
Nash Waste Water Treatment Works Turbine
Wind Onshore · Operational
2.51.8 km
Liberty Steel Power Station
Biomass (dedicated) · Operational
91.9 km
Solutia UK Ltd
Wind Onshore · Operational
52 km
Geraint Thomas National Velodrome - Solar
Solar Photovoltaics · Operational
2.2 km
Uskmouth Power Station, West Nash Road - Battery Storage Facility
Battery · Under Construction
1202.3 km
Llanwern Solar Farm & Battery Storage
Solar Photovoltaics · Operational
752.3 km

How big is Llanwern Solar Farm & Battery Storage?

REPD does not record an installed capacity for Llanwern Solar Farm & Battery Storage.

Who operates Llanwern Solar Farm & Battery Storage?

REPD records the operator as NextEnergy Capital LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Llanwern Solar Farm & Battery Storage approved and built?

The application was submitted on 2018-02-20. Permission was granted on 2019-04-18, 14 months later. The site became operational on 2021-03-01, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6983.