Renewable sites › Nailsea Rescue Centre, Nailsea - Solar Panels
Nailsea Rescue Centre, Nailsea - Solar Panels
Nailsea Rescue Centre, Nailsea - Solar Panels is operational in North Somerset, and has been generating since 2021-07-01.
Planning and build timeline
| Application submitted | 2021-05-10 |
| Permission granted | 2021-08-06 3 months after submission |
| Operational | 2021-07-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Somerset’s record on solar
North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bristol Airport Solar Farm Solar Photovoltaics · Under Construction | — | 7 km |
Smart Systems Limited, Arnolds Way - Solar Panels Solar Photovoltaics · Under Construction | 2.93 | 7.3 km |
Arnolds Way, Yatton - Solar Panels Solar Photovoltaics · Under Construction | 0.84 | 7.4 km |
Epic Long Ashton, Phase 1 - 3 Office Buildings Solar Photovoltaics · Under Construction | 1.05 | 8.3 km |
Avonmouth Port - extension Wind Onshore · Operational | 9 | 8.5 km |
Iwood Lane Solar Farm Solar Photovoltaics · Operational | 8 | 9 km |
Twin Elm Solar Farm Solar Photovoltaics · Operational | 1 | 9.2 km |
Avonmouth Port Wind Onshore · Operational | 6 | 9.3 km |
How big is Nailsea Rescue Centre, Nailsea - Solar Panels?
REPD does not record an installed capacity for Nailsea Rescue Centre, Nailsea - Solar Panels.
Who operates Nailsea Rescue Centre, Nailsea - Solar Panels?
REPD records the operator as Avon Fire and Rescue Service. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nailsea Rescue Centre, Nailsea - Solar Panels approved and built?
The application was submitted on 2021-05-10. Permission was granted on 2021-08-06, 3 months later. The site became operational on 2021-07-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9043.