Renewable sitesNailsea Rescue Centre, Nailsea - Solar Panels

Nailsea Rescue Centre, Nailsea - Solar Panels

Nailsea Rescue Centre, Nailsea - Solar Panels is operational in North Somerset, and has been generating since 2021-07-01.

Capacity
as recorded in REPD
Operational
Status
since 2021-07-01
Solar Photovoltaics
Technology
Avon Fire and Rescue Service
North Somerset
Authority
England

Planning and build timeline

Application submitted2021-05-10
Permission granted2021-08-06
3 months after submission
Operational2021-07-01

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Somerset’s record on solar

North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset

Other built sites within 15 km

SiteMWDistance
Bristol Airport Solar Farm
Solar Photovoltaics · Under Construction
7 km
Smart Systems Limited, Arnolds Way - Solar Panels
Solar Photovoltaics · Under Construction
2.937.3 km
Arnolds Way, Yatton - Solar Panels
Solar Photovoltaics · Under Construction
0.847.4 km
Epic Long Ashton, Phase 1 - 3 Office Buildings
Solar Photovoltaics · Under Construction
1.058.3 km
Avonmouth Port - extension
Wind Onshore · Operational
98.5 km
Iwood Lane Solar Farm
Solar Photovoltaics · Operational
89 km
Twin Elm Solar Farm
Solar Photovoltaics · Operational
19.2 km
Avonmouth Port
Wind Onshore · Operational
69.3 km

How big is Nailsea Rescue Centre, Nailsea - Solar Panels?

REPD does not record an installed capacity for Nailsea Rescue Centre, Nailsea - Solar Panels.

Who operates Nailsea Rescue Centre, Nailsea - Solar Panels?

REPD records the operator as Avon Fire and Rescue Service. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nailsea Rescue Centre, Nailsea - Solar Panels approved and built?

The application was submitted on 2021-05-10. Permission was granted on 2021-08-06, 3 months later. The site became operational on 2021-07-01.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9043.