Iwood Lane Solar Farm is an operational 8 MW solar farm in North Somerset, generating since 19 December 2014. Planning permission was granted on 14 May 2014, 5 months after submission. Operator of record: Wessex Solar Energy.
Planning and build timeline
| Application submitted | 12 December 2013 |
| Permission granted | 14 May 2014 5 months after submission |
| Operational | 19 December 2014 7 months after consent |
Screening a site of your own?
North Somerset approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Iwood Lane Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Somerset’s record on solar
North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1 | 0.4 km |
Solar Photovoltaics · Operational | 7.1 | 2.5 km |
Solar Photovoltaics · Under Construction | 0.84 | 4.7 km |
Solar Photovoltaics · Under Construction | 19.8 | 4.8 km |
Solar Photovoltaics · Under Construction | 2.93 | 4.9 km |
Solar Photovoltaics · Operational | 8.3 | 5.1 km |
Solar Photovoltaics · Operational | 7.2 | 5.4 km |
Solar Photovoltaics · Under Construction | — | 6.1 km |
How big is Iwood Lane Solar Farm?
Iwood Lane Solar Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Iwood Lane Solar Farm?
REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Iwood Lane Solar Farm approved and built?
The application was submitted on 12 December 2013. Permission was granted on 14 May 2014, 5 months later. The site became operational on 19 December 2014, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1886.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode