Novarly ParcelRenewable sites

Renewable sitesIwood Lane Solar Farm

Iwood Lane Solar Farm

Iwood Lane Solar Farm is operational in North Somerset with a recorded capacity of 8 MW, and has been generating since 2014-12-19.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-12-19
Solar Photovoltaics
Technology
Wessex Solar Energy
North Somerset
Authority
England

Planning and build timeline

Application submitted2013-12-12
Permission granted2014-05-14
5 months after submission
Operational2014-12-19
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Somerset’s record on solar

North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset

Other built sites within 15 km

SiteMWDistance
Twin Elm Solar Farm
Solar Photovoltaics · Operational
10.4 km
Congresbury Solar Farm
Solar Photovoltaics · Operational
7.12.5 km
Arnolds Way, Yatton - Solar Panels
Solar Photovoltaics · Under Construction
0.844.7 km
Bowerhouse Farm (extension)
Solar Photovoltaics · Under Construction
19.84.8 km
Smart Systems Limited, Arnolds Way - Solar Panels
Solar Photovoltaics · Under Construction
2.934.9 km
Bowerhouse Farm
Solar Photovoltaics · Operational
8.35.1 km
Towerbrook Farm (Banwell Solar Farm)
Solar Photovoltaics · Operational
7.25.4 km
Bristol Airport Solar Farm
Solar Photovoltaics · Under Construction
6.1 km

How big is Iwood Lane Solar Farm?

Iwood Lane Solar Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Iwood Lane Solar Farm?

REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Iwood Lane Solar Farm approved and built?

The application was submitted on 2013-12-12. Permission was granted on 2014-05-14, 5 months later. The site became operational on 2014-12-19, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1886.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council