Novarly ParcelRenewable sites

Renewable sitesTwin Elm Solar Farm

Twin Elm Solar Farm

Twin Elm Solar Farm is an operational 1 MW solar farm in North Somerset, generating since 25 July 2012. Planning permission was granted on 11 June 2012, 3 months after submission. Operator of record: Lightsource BP.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 25 July 2012
Solar Photovoltaics
Technology
Lightsource BP
North Somerset
Authority
England

Planning and build timeline

Application submitted19 March 2012
Permission granted11 June 2012
3 months after submission
Operational25 July 2012
1 months after consent

Screening a site of your own?

RedlineUK · £39

North Somerset approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Twin Elm Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Somerset’s record on solar

North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
80.4 km
Solar Photovoltaics · Operational
7.12.2 km
Solar Photovoltaics · Under Construction
19.84.4 km
Solar Photovoltaics · Under Construction
0.844.6 km
Solar Photovoltaics · Operational
8.34.8 km
Solar Photovoltaics · Under Construction
2.934.8 km
Solar Photovoltaics · Operational
7.25 km
Solar Photovoltaics · Operational
85.8 km

How big is Twin Elm Solar Farm?

Twin Elm Solar Farm has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Twin Elm Solar Farm?

REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Twin Elm Solar Farm approved and built?

The application was submitted on 19 March 2012. Permission was granted on 11 June 2012, 3 months later. The site became operational on 25 July 2012, 1 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1208.