Twin Elm Solar Farm

Twin Elm Solar Farm is operational in North Somerset with a recorded capacity of 1 MW, and has been generating since 2012-07-25.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-07-25
Solar Photovoltaics
Technology
Lightsource BP
North Somerset
Authority
England

Planning and build timeline

Application submitted2012-03-19
Permission granted2012-06-11
3 months after submission
Operational2012-07-25
1 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Somerset’s record on solar

North Somerset has decided 39 solar farms and approved 95%, taking a median of 2.9 months. See every solar farm decision in North Somerset

Other built sites within 15 km

SiteMWDistance
Iwood Lane Solar Farm
Solar Photovoltaics · Operational
80.4 km
Congresbury Solar Farm
Solar Photovoltaics · Operational
7.12.2 km
Bowerhouse Farm (extension)
Solar Photovoltaics · Under Construction
19.84.4 km
Arnolds Way, Yatton - Solar Panels
Solar Photovoltaics · Under Construction
0.844.6 km
Bowerhouse Farm
Solar Photovoltaics · Operational
8.34.8 km
Smart Systems Limited, Arnolds Way - Solar Panels
Solar Photovoltaics · Under Construction
2.934.8 km
Towerbrook Farm (Banwell Solar Farm)
Solar Photovoltaics · Operational
7.25 km
The Grange
Solar Photovoltaics · Operational
85.8 km

How big is Twin Elm Solar Farm?

Twin Elm Solar Farm has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Twin Elm Solar Farm?

REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Twin Elm Solar Farm approved and built?

The application was submitted on 2012-03-19. Permission was granted on 2012-06-11, 3 months later. The site became operational on 2012-07-25, 1 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1208.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council